The short version
- Route: from Highway 4206 at Koh Klang on the mainland, across Khlong Chong Lat, to rural road KB.5035 on Koh Lanta Noi. Koh Lanta Noi is already linked to Koh Lanta Yai by the Siri Lanta bridge.
- Size: a bridge of about 1,780 metres plus about 747 metres of approach road, roughly 2.5 km of new road, built for more than 10,000 vehicles a day.
- Money: a budget of about 1.85 billion baht, financed with World Bank loans approved by the Thai Cabinet in July 2026 and government funds.
- Contract: signed by the Department of Rural Roads on 31 August 2026, with 1,080 days to build.
- Opening: the contract period ends on 15 August 2029. Thai projects often run late, so 2029 is the planning year and the month is provisional.
What it replaces
Every car, truck and taxi reaches Koh Lanta today on a vehicle ferry with fixed hours and limited deck space. Queues are long in high season and on Thai holidays, and a late landing at Krabi airport can mean a night on the mainland. The bridge removes that bottleneck: arriving late, moving building materials and reaching hospital on the mainland all become a drive.
Timeline
- July 2026: Cabinet approves the World Bank loan for the Koh Lanta and Songkhla bridges
- August 2026: winning bidders announced; contract signed on 31 August
- November 2026: construction scheduled to begin
- 2027-2028: construction; the ferries keep running and queues may grow with construction traffic
- 2029: planned opening
What it means for land on Koh Lanta
We do not publish price forecasts. Three things are certain enough to plan around:
- Year-round access: the island stops depending on ferry schedules and sea conditions for road traffic.
- Construction logistics: trucks reach a building site without a ferry crossing, which simplifies any project that starts after the opening.
- Timing: a resort or villa project designed and permitted during 2027-2028 can open about when the bridge does.
Cape Shambhala lies near the southern end of Koh Lanta Yai's west-coast road. See location and access and the fact sheet.
Sources: The Nation, Cabinet approves World Bank loan; Explera, Koh Lanta and Songkhla bridges; Siam Real Estate, construction from November 2026; Amazing Lanta, bridge set for 2029.